For a given project (or user), the jobs currently running in the system should not exceed a certain amount of cpu-time Q(project). The current cpu-time of a project T(project) is defined as the sum of all remaining cpu-times of the running jobs of a project (number_of_resources*remaining_walltime). When the scheduler encounters a job with t (number_of_resources*walltime) > Q(project)-T(project) it should not be scheduled and be kept in the FIFO.